Living Room finale

I've left the wall in the living room to cover HVAC lines forever, and since Christmas is coming we felt it was time to finish that.  Previously I had gotten drywall up:


Assembled new trim that's close to matching the existing chair rail:


Cut and painted baseboard:

Installed chair rail, baseboard and painted with primer.


And finished paint just before Christmas.



A few small things...

Decided while the 1st floor has been mostly done for awhile, staring at HVAC plumbing lines behind TV was old, so decided to box those in with drywall.  And of course none of the walls are plumb here... Hence the pieced-together 2x4 blocking.


Some drywall and mud, then good as new.


Also took opportunity to remove the last door on sunporch:


Fit new door in opening:

Shim and screw it in.



Snowblower sidetrip

You may recall that I rebuilt the snowblower this summer. And that went well.  I got things running, reassembled and ready.  And after a few months found this on garage floor:


Yeah, that's a leak. Turns out to be gear lubricant from the gear case, one of the few things I do NOT rebuild over the summer, so I guess I have a new project.

Time to take snowblower auger off:


Remove auger from housing:


And let's take it apart to see if there's a seal that can be replaced:


So take things apart, clean them out and order replacement lube and seals for gear box.


Oh? And see the green seal on the shaft below? That I can't replace because the impeller is completely rusted to the drive shaft.  I tried using penetrating oil and propane torch to heat impeller but that proved useless - the rust has fused these together.


Update: fully assembled and working, but I won't share how many times it took to get the driveshaft and augers assembled correctly (hint: neither the driveshaft nor augers are symmetric so there are many wrong ways to assemble them).




Glazed and Confused

Well, we decided the barn could just use more natural light.  Recall this past summer we added a new window to the barn. Well we could use another one.  Lather, rinse, repeat:

We need more light in the back wall on this side:


From barn, we have a couple of remaining old windows. So grab one and strip old paint:


Remove dried/cracked glazing from other side:


Invoke your inner child and roll out glazing like Play-Doh:


And mush it down at 45 degrees:


And we have a reglazed window. We need to let glazing dry (cure) for several weeks before we try to paint anything.


Garage, other side, part deux

We don't have a ton of pictures even though good progress was made.   Short story: we finished all the termite damage replacement, simil...