We were able to get the patio laid and begin moving onto the walkway.
Onto the walkways
We got pavers
We finally got some pavers installed. Here's how
Setup chop saw with masonry blade to cut a bunch of bricks in 1/2. The pattern will need some 1/2 bricks...
Yard work
We continue to make slow progress on the walks, mostly due to weather and life schedules interfering.
While we've had some rain, I wanted to get my pond pump working and - it was not. The pump runs but no water. So we need to wade into pond to investigate.
Next we're pretty close to laying pavers, so we fine-tune the patio elevation. Make a grid with approx 2-3' squares and measure height in each one.
Delayed update
Not a lot of updates due to life, holiday and more. But some progress for sure.
Garage, other side, part deux
We don't have a ton of pictures even though good progress was made. Short story: we finished all the termite damage replacement, simil...
-
We need to get bathroom plumbing done. But since the 2nd floor bath is directly above the 1st floor bathroom, it only makes sense to plumb b...
-
Trim: "Pure White" HGSW4006 Living Room: "Pussywillow" HGSW1494 Bathroom #2: "Icy Avalanche" HGSW1497 Kitchen...
-
So both from termites and water damage (due to lack of gutters) we need to clean up a lot of the bottom plates. First remove exterior siding...