We have (another) bathroom?

Well, it's not 100% done as the cosmetics need to be completed. But hey, it's fully working.

Cut backsplash for sinks.


Attached them to wall and caulked seam.


Because of window trim and vanity itself, we can't get flush to right wall. So we need to fill the gap and apply a piece of backsplash on side to prevent water from running down the wall.


Backsplash applied, still need to caulk, paint and close opening in front.


Installed black hardware to match other cabinets

Put in electrical boxes (and indeed, the wires I ran a year ago and buried in walls were exactly where they needed to be).


Double vanity almost done.



Short Update

I haven't posted much simply because we haven't done a lot on house due to other things. But we do have a few quick updates.

Gutters started to get installed but were quickly thwarted by rain.  The backside of house is mostly done and I got to see them work firsthand.


As for that rain we finally got, you can see our waterproofing on new brick steps is holding up well:


We still have work to do in bathroom, but we were able to get shower valve in quickly and have a second functional shower now.


Beach Detour

We haven't posted updates much because we were sidetracked with some vacation time in NH and FL, Covid somewhere in between and regular work stuff.

Also, while working on the house the beach house has become a bit of a deferred maintenance nightmare, so while enjoying this week I've been slowly working on some beach projects.

One of the posts for the gate rotted out, so I had to replace it.




The small paver area was crumbling and overtaken with crabgrass.  So we removed all the pavers:


Cleaned out weeds:

Installed new timbers and weedblock.

Reinstalling pavers and wood chips coming next.

Garage, other side, part deux

We don't have a ton of pictures even though good progress was made.   Short story: we finished all the termite damage replacement, simil...