It's time for a real closet.

We're building a large walk-in closet in bedroom and it's time to get moving.  We need to remove one wall, which is going to be a very dusty mess.  So we're building the 1st new wall for the closet first in an attempt to contain dirt/dust away from the bedroom itself.

This is the wall to be removed:


Put up some plastic sheeting to contain saw dust while we build new wall.


Frame one side of wall


and both halves are framed.  There's a large opening because we're using two pocket doors.

Install track for pocket doors from a header.


Install metal studs where pocket doors will slide.



And drywall for two sides of closet (we'll fill in the small upper section shortly).



Basement done?

The basement isn't 100% done - but it's back in a workable state.  We'll make some more improvements later, but need to get back to some real house projects.

Table saw is back and now the floor is actually level.  (We used to have to shim one of the legs.)



Rebuilt the miter saw station, but only on right side.  Currently mulling different use of the space on left side...


My portable air filter on casters (and junk collector since it has a lot of space on top) is good.



Dust collector for saw/planer is moved to new location and re-ran PVC pipe for ductwork.  Also reconfigured the dust collector - the blue barrel is now 1st of two stage separator, which collects the majority of sawdust before it gets to large filter and plastic bag (on the right).




Basement is 95% done

Basement isn't glamorous.  But solving dust and organization help enable other things. So we bit off the rest of the basement floor project this weekend. (We still have one small area, but that needs a repair, as leveler won't fix it.)

First remove everything, and clean end-to-end.


A short time lapse of 2 hours.


And voila, we have a new floor.

You can see the orange foam line in the background, that's the small section that needs some repair, but it's not important to solve immediately.



Dust and more dust

Many of the basement changes are an attempt to reign in dust, which is rampant.  We're doing three primary things.

1. Pouring new floor with self-leveler to make it both level and smooth - far easier to clean after working.  We've got about 40% of floor done.


2. Building an air filter to remove as much airborne dust as possible. This will have 20x20 filters in side openings and a large fan on top to draw dusty air in.


3. Reworking dust collector. It's got a very good filter but was already clogged. So we're building a two-stage filter to separate as much dust/debris before it gets to filter.  

Before cleaning (and the inside is worse).


After extracting as much sawdust from interior, it's a bit messy.


Remounting dust collector on a drum, which separates a lot of heavy/larger debris (wood chips)  before sending remainder to the filtr.



Basement dis-organization

Basement organization is progressing, albeit slowly.

Stair supports are done, which offers decent storage as well.


When we demoed the kitchen, I kept a few drawers thinking they would be decent floor storage. 


Install casters and voila. Instant rolling floor storage.


Sand and paint columns which were rusty.


Clean out way too much wood and free up needed space.




Paint and more

We got the first basement stair post installed, which means we were able to move onto the other side.


Removed the 2nd post and indeed, the rock "supporting" this side easily came up.



Removed sands, mix more concrete and fill hole.  Hurry up and wait for it to dry.


In the meantime, we cut in paint for the sunroom at ceiling. Yes. another grey room.



Basement Detour

We still need to finish lots more in the basement, but one area of concern is the basement stairs and support posts.  The support posts sit on two rocks (yes, literal rocks) in the basement floor, and the posts need to be replaced with proper 4x4s.  Likewise, the stairs feel "soft" (eg: they flex) when you walk up/down them, which is a sign they're not super secure or supported.

My intent was remove the wooden posts and install new 4x4 on the existing rocks - we'd like to remove them, but fear these rocks were large and went perhaps 10-12" deep into concrete floor.

Spoiler alert: they don't.  Old post on a rock:


Install a temporary lollycolumn so we can remove the old post.


Remove old post and guess what? The rock is barely 3" thick and is just resting on sand.  


So we dig out the sand about 12" deep, run to Lowes for a few bags of concrete and make a new footing for 4x4 post:


Because we only have one temp lolly column, we'll have to let concrete set and install new 4x4 before we can repeat all of this on the other side.  In the meantime, we fix the "soft" stairs by adding a third stringer down the middle.

Frist cut to match existing stairs (as closely as we can, cuz they're not perfect).


Install stringer and shim each step as needed (did we mention they're not terribly consistent?)


Once we get both 4x4 posts replaced, we'll add cross member to support all three stringers.


Garage, other side, part deux

We don't have a ton of pictures even though good progress was made.   Short story: we finished all the termite damage replacement, simil...