Generator! And a little siding.

Given power issues here, we decided that a generator was probably a good investment.  And of course, to make it easier we got a transfer switch to make connecting/disconnecting easier.  So it went from mounting transfer switch and pulling wires


Connecting transfer switch to cable running outside

Pulling cable thru an already existing hole in foundation (water line used to be here)

Mounting receptacle for generator



And testing generator hookup:

Got a small amount of siding done after generator:



Soffits and more

Wanted to get all scaffolding down, which means all loose ends need to be completed - including soffits and trim.  Where the dormer meets the house creates a very tight/awkward space so instead of trying to shingle in tight quarters, I decide to give sheet PVC a whirl

Had to drive all over to find a 4x8 sheet, but I finally did.


Got PVC in corner soffit:

As well as back/side soffits cleaned up and (eventually) ready for gutters next spring.  Removed all scaffolding to move to front of house.



Finishing another side of shingles

In an effort to get things outside mostly done before snow arrives, we've been trying to get all shingling done. Made slow progress over the week getting this shingled. It's been exposed for almost a year and needs to be covered up:


Got shingles completed on side:


As well as the back side dormer. The angle of both rooflines made cutting shingles a bit more work than I would've liked.

Replaced rotted window frame on barn:


And removed both windows in barn to reglaze the panes and repaint.



Busy Weekend...

Spent most of the weekend finishing shingles on right side of house.  Stripped paint to remove olive green and painted trim before shingles were installed.



And shingles went from this 


to this

And yes, we matched the "artwork" on this gable end to the other:

Also was able to mount a small work platform under Catherine's bedroom windows to work on siding there next week.



More Shingles

Because we can't escape the shingles...  Got a few courses applied on right side.


Had to apply PVC trim to corner with 2nd bathroom

Finished top 2 courses on kitchen exterior:


After PVC corner trim was applied (above) was able to shingle up to top of 2nd windows.  Need to strip olive green paint before we shingle the rest.

Oh and re-attached the electrical service too. :)



Inside Outside

Spent time trying to get Right side of the house shingled, but also some other projects came along for good measure.  

One of those side projects is need to complete floor in barn (aka: garage).  We already have two inside parking spots done with old bricks as pavers, but we don't have enough bricks for the remaining floor. And leaving a dirt floor isn't an option, so we're digging out 4", leveling and going to pour concrete.

Left side storage/workspace:


Right rear for bikes and more:


More barn work: one window is broken, so we have a few leftover spares. Prepping window by removing old and cracked glazing and re-glazing the exterior side of panes:


And painting the interior. We'll paint the exterior, but glazing needs to dry for 1-2 weeks.


And one more soffit end from roof to remake in PVC



Garage, other side, part deux

We don't have a ton of pictures even though good progress was made.   Short story: we finished all the termite damage replacement, simil...