It didn't go as quickly as we might've thought, but the walkway paver base is done.  In short, excavate grass/dirt and fill with gravel  leaving approx 3" for paver and sand.

Installed the last section of downspout drain under patio.


Reuse existing stone dust and level patio base as much as possible.


After walkway base is dug, apply gravel and run compactor over and over again.


Walkway from house to driveway is essentially same as before but splits towards front door.


Front entrance with walkway widened from 4' to 6'.


Spread the remaining gravel on patio. We're short, but that's easy to remedy later.