Bathroom Progress

 With things in the kitchen moving ahead, while we wait for countertops we're moving onto bathroom and other projects.  Today we removed toilet and laid backerboard on the floor to prepare for floor tile. We will also be drywalling over the existing walls shortly.  Everyone's favorite: siphoning water out of toilet before removing:


Removing old plumbing for sink and toilet:



Room stripped and floor clean

The floor has a slight crown which dips down on the left wall against the kitchen.  So I laid leftover shingles on that side to level the backerboard.  This won't affect the floor because it's under the toilet and sink vanity.


A little modified thinset spread:

backerboard laid in thinset, and joints taped/sealed.  Will put waterproofing over backerboard once it cures for a day or two:


No comments:

Post a Comment

Garage, other side, part deux

We don't have a ton of pictures even though good progress was made.   Short story: we finished all the termite damage replacement, simil...